Industry Information

Project Goals

  1. Maximize improvements within the program budget of $62 million.
  2. Improve safety and efficiency of the transportation network while supporting connectivity for the local community.
  3. Provide a durable and maintainable transportation infrastructure allowing for future expansion.
  4. Minimize impacts to the traveling public during construction while safely delivering the project by November 1, 2023.
  5. Deliver the project using a diverse workforce.

Request for Qualifications (RFQ) – December 7, 2020

PAUSED

To view the RFQ, please click here.

For questions or clarifications regarding the RFQ, please submit form DB-107 Request for Clarification RFQ to i70csfg@modot.mo.gov. The form can be found in the list below. All Requests for Clarification will be answered publicly on this website at the link below. The name of the individual or firm submitting the Request for Clarification will not be released.

The following are Design-Build forms which potential companies will need to submit SOQs (Statement of Qualifications).

DB-101 I-70 Cave Springs to Fairgrounds Major Participant Info

DB-102 I-70 Cave Springs to Fairgrounds Reference Project Summary

DB-103 I-70 Cave Springs to Fairgrounds Resume Summary.pdf

DB-104 I-70 Cave Springs to Fairgrounds Receipt of Addenda.pdf

DB-105 I-70 Cave Springs to Fairgrounds Conflict of Interest

DB-107 I-70 Cave Springs to Fairgrounds Request for Clarification RFQ

DB-110 I-70 Cave Springs to Fairgrounds Com of Key Personal

DB-802 I-70 Cave Springs to Fairgrounds Debarment - Suspension


Industry Meeting

Industry Meeting Attendee List