The Bismarck-Mandan Metropolitan Planning Organization (MPO) has initiated a study to determine operational improvements
Project Schedule |
2015 | 2016 | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar | Apr | May | Jun | Jul | |
Project Kickoff | Mid-August 2015 | |||||||||||
Existing Conditions Evaluation | Late August through December 2015 | |||||||||||
Public Meeting #1 | Mid-January 2016 | Project Kickoff | ||||||||||
Alternatives Development | February through early March 2016 | |||||||||||
Public Meeting #2 | Mid-March 2016 | Alternatives Development | ||||||||||
Alternatives Evaluation | Late March through early April 2016 | |||||||||||
Public Meeting #3 | Mid-April 2016 | Alternatives Evaluation | ||||||||||
Final Report Draft | May 2016 | |||||||||||
Commission & NDDOT Management Presentations | Mid-June 2016 | |||||||||||
Final Report | July 2016 |