Bismarck-Mandan Corridor Improvement

About the project

The Bismarck-Mandan Metropolitan Planning Organization (MPO) has initiated a study to determine operational improvements

The corridor study includes:

Project Schedule

2015 2016
AugSepOctNovDec JanFebMarAprMayJunJul
Project Kickoff Mid-August 2015
Existing Conditions Evaluation Late August through December 2015
Public Meeting #1 Mid-January 2016
Project Kickoff
Alternatives Development February through early March 2016
Public Meeting #2 Mid-March 2016
Alternatives Development
Alternatives Evaluation Late March through early April 2016
Public Meeting #3 Mid-April 2016
Alternatives Evaluation
Final Report Draft May 2016
Commission & NDDOT Management Presentations Mid-June 2016
Final Report July 2016